LA CRESCENTA — A San Dimas-based construction company is seeking nearly $100,000 from the Crescenta Valley Water District for work on a 12-inch water main along three blocks of Foothill Boulevard, according to a lawsuit filed in Glendale Superior Court.
MNR Construction Inc. claims it’s owed $95,903 in unpaid interest and work bills for installing a water main on the 2700, 2800 and 2900 blocks of Foothill Boulevard, but water district representatives argue the project amendments that caused the snafu were negotiated in good faith.
In September 2007, MNR Construction entered into a $517,619 contract with the water district to install the water main.
But the water line could not be installed as initially designed because “there were a lot more underground utilities than the water district was aware of that didn’t allow this 12-inch water main to go as it was originally planned,” said the company’s attorney, Randall Pitre.