Glendale finds a way to pay for Laemmle Lofts project

City officials do fancy financial footwork to develop mixed-use project.

November 04, 2013|By Daniel Siegal, daniel.siegal@latimes.com

The city of Glendale may have found a way to resolve a development quandary left by the dissolution of its redevelopment agency. Resolving that quandary will allow the mixed-use Laemmle Lofts development to move forward, city officials said.

The project originally was intended to rely upon redevelopment funds. But because the state dissolved all redevelopment agencies, that funding now is problematic.

The proposed project, which was approved by the city in November 2011, would include a five-screen Laemmle theater, 42 residential units and 6,000 square feet of commercial space and a subterranean parking structure.

Advertisement

Phil Lanzafame, the city's economic development manager, said Glendale found a way to provide funds to cover any losses the so-called “taxing entities” might incur from the project moving forward.

To do that, the city council approved using $728,050 in a tax-revenue-sharing agreement with the city, Los Angeles County, Glendale Unified School District and Glendale Community College in 4-1 vote, with Mayor Dave Weaver opposed.

“It's worse for them to develop the project [than dissolve its development agreement], so what we have proposed is we write a check to each of the taxing entities with the dollars that are generated from our share to make them whole,” he said.

Under the original agreement approved by the redevelopment agency, the project would receive $3.6 million — $2.6 million in direct financial assistance from redevelopment funds currently in a holding account, and a piece of land valued at $1 million.

The first iteration of the agreement contained only $1.5 million in financial assistance, but the city later moved to add an additional $1.1 million so the project could add the parking structure.

Getting approval for that additional $1.1 million is what triggered the review of the whole project, Lanzafame said Friday.

With the end of redevelopment, the money that would have funded the project was redirected to the local school district, community college and the county, as well as other entities.

Under the revised agreement, those entities would give up that funding due them. Los Angeles County would forgo $1.39 million, Glendale Unified would give up $735,615 and Glendale Community College would chip in $140,341.