Op-Ed: Glendale's growth plans have mobility in mind

January 29, 2014|By Scott Ochoa
  • A construction project between Brand Blvd. and Orange Street in downtown Glendale where several properties are under development, many of them for apartments, on Wednesday, November 27, 2013.
A construction project between Brand Blvd. and Orange… (Tim Berger / Staff…)

In response to the Glendale News-Press article "Massive building boom troubles Caltrans" published on Friday, Jan. 10, 2014: The city of Glendale has executed a policy of smart and sustainable development in and around our downtown core. Not only does this make sense economically and environmentally (placing uses within close proximity to one another and reducing folks' reliance on automobiles), but it also allows us to better leverage our strategic infrastructure investments. Further, the city has diligently and proactively complied with state mandates to accommodate growth in jobs and housing while investing resources to minimize local and regional impacts on the transportation infrastructure. Over the past two decades, the city has dedicated approximately $100 million to transportation and mobility improvement projects. The following are just a few highlights:

Improving the efficiency of city on-ramps and off-ramps — Since 1990, the Glendale has been improving signals, realigning and widening ramps, and modifying travel lanes on ramps throughout the city. By 2019, the city will have improved in some fashion every freeway ramp leading to and from Glendale.

Advertisement

Funding large-scale street improvement projects — Glendale has placed an emphasis on improving major streets that serve as alternatives to the regional freeway network, and properly accommodating new development. Some examples include:

  • $34 million to construct the Fairmont Avenue Bridge from the 134 Freeway directly into the expanding Disney and DreamWorks Campuses, thus alleviating the impact on the San Fernando Rail Corridor;

  • $14.5 million dedicated to the 5 Freeway and Western Avenue interchange, including widening Flower Street and improving the northbound on-ramps and off-ramps at Western Avenue;

  • $9.6 million for street improvements to Colorado Street and Central Avenue — road-widening, improved lighting, new bus stop shelters, upgraded signals, and a bike lane on Central Avenue were installed as a result of the Downtown Specific Plan.

Providing local transit with connections to the regional network — The city has made a commitment to provide quality local transit through the Glendale Beeline, serving 2.2 million riders annually. Our grant-funded Maintenance Facility serves the nine-route, 34 bus fleet, which consists entirely of 40-foot low-floor CNG buses, a first for any public transit operator in Los Angeles County.